How is capacity planning done?
First, the available time of each work center is worked out: number of shifts, working days, allowance for maintenance and breaks. Then the load is calculated by adding up the operation times (setup and run time) in the routing of each work order. Load is compared with capacity. If load exceeds capacity, the job is scheduled earlier or later, a shift is added, the work is subcontracted or moved to an alternative machine. ERP can redo this calculation as orders change. Machine breakdowns, maintenance and shift patterns are also deducted from capacity during the calculation, so planned maintenance must be written into the capacity plan as well.